Looks like the slurry wall work on Bldg 3 site has been completed.
Looks like they are using the Bldg 5 site as a staging area for Bldg 4 steel deliveries.
BeeLine is offline   Reply With Quote
Old 02-21-2018, 07:54 AM   #282
BeeLine
Senior Member
 
Join Date: Jan 2012
Posts: 7,759
Re: MIT East Campus - Kendall Square Gateway | Cambridge

bld 4 site Going up











Bldg 3 site Going down.

Last edited by BeeLine; 02-21-2018 at 08:05 AM.
BeeLine is offline   Reply With Quote
Old 02-21-2018, 08:07 AM   #283
BeeLine
Senior Member
 
Join Date: Jan 2012
Posts: 7,759
Re: MIT East Campus - Kendall Square Gateway | Cambridge

Slurry rig working along the north side on the Bldg 5 site.




BeeLine is offline   Reply With Quote
Old 03-11-2018, 09:07 AM   #284
BeeLine
Senior Member
 
Join Date: Jan 2012
Posts: 7,759
Re: MIT East Campus - Kendall Square Gateway | Cambridge

Looks like the slurry wall operation has been completed on all three building sites. Rigs and supporting equipment has been removed.
At the site of building 3 they look to be getting ready to dig down.


At the building 4 site steel work, below ground level continues.




And renovating the white building.


Looks like the building 5 site is back to being used as a stagging area, especially for steel deliveries.

BeeLine is offline   Reply With Quote
Old 03-30-2018, 05:15 AM   #285
BeeLine
Senior Member
 
Join Date: Jan 2012
Posts: 7,759
Re: MIT East Campus - Kendall Square Gateway | Cambridge

On Bldg 3 site they have started excavation and install some very heavy duty steel.



At Bldg 4 site we have more steel going vertical.









At the Bldg 5 site slurry wall work has been completed and excavation of the site has begun.






Last edited by BeeLine; 03-30-2018 at 05:26 AM.
BeeLine is offline   Reply With Quote
Old 03-31-2018, 09:00 PM   #286
BeeLine
Senior Member
 
Join Date: Jan 2012
Posts: 7,759
Re: MIT East Campus - Kendall Square Gateway | Cambridge

Work on One Broadway continues.

New Dunks opened on the Third street side of the building.




On the Broadway side work on the new lobby continues.






Last edited by BeeLine; 03-31-2018 at 09:33 PM.
BeeLine is offline   Reply With Quote
Old 04-01-2018, 02:18 PM   #287
Czervik.Construction
Senior Member
 
Join Date: Apr 2013
Location: NYC
Posts: 994
Re: MIT East Campus - Kendall Square Gateway | Cambridge

Thank goodness that the dunkies is open during all of this.
Czervik.Construction is offline   Reply With Quote
Old 04-12-2018, 06:55 AM   #288
BeeLine
Senior Member
 
Join Date: Jan 2012
Posts: 7,759
Re: MIT East Campus - Kendall Square Gateway | Cambridge

One Broadway

Earth removal continues at the Bldg 3 site.


Foreground is the Bldg 3 site. Background Bldg 4 site.



Bldg 4 site.




Bldg 4 foreground Bldg 3 background

Bldg 5 site. Bracing going in and earth removal has begun.




Last edited by BeeLine; 04-12-2018 at 07:09 AM.
BeeLine is offline   Reply With Quote
Old 06-10-2018, 09:05 PM   #289
BeeLine
Senior Member
 
Join Date: Jan 2012
Posts: 7,759
Re: MIT East Campus - Kendall Square Gateway | Cambridge

Looks like they are starting site prep for Bldg !. New signs are up on the site fences.






BeeLine is offline   Reply With Quote
Old 06-10-2018, 09:16 PM   #290
BeeLine
Senior Member
 
Join Date: Jan 2012
Posts: 7,759
Re: MIT East Campus - Kendall Square Gateway | Cambridge

Renovation/Remodel of the old Red Cross Bldg continues.





Looks like some major work on the front of the bldg.
BeeLine is offline   Reply With Quote
Old 06-10-2018, 09:21 PM   #291
BeeLine
Senior Member
 
Join Date: Jan 2012
Posts: 7,759
Re: MIT East Campus - Kendall Square Gateway | Cambridge

Remodel of One Broadway continues.



BeeLine is offline   Reply With Quote
Old 06-10-2018, 10:26 PM   #292
BeeLine
Senior Member
 
Join Date: Jan 2012
Posts: 7,759
Re: MIT East Campus - Kendall Square Gateway | Cambridge









BeeLine is offline   Reply With Quote
Old 06-10-2018, 10:28 PM   #293
odurandina
Senior Member
 
odurandina's Avatar
 
Join Date: Dec 2015
Posts: 3,599
Re: MIT East Campus - Kendall Square Gateway | Cambridge

Thanks Beeline!
odurandina is online now   Reply With Quote
Old 06-10-2018, 11:59 PM   #294
Jouhou
Senior Member
 
Jouhou's Avatar
 
Join Date: Nov 2015
Location: Portsmouth, NH
Posts: 551
Re: MIT East Campus - Kendall Square Gateway | Cambridge

I just dug through this whole thread, do we know what exactly is supposed to be replacing eastgate?
Jouhou is online now   Reply With Quote
Old 06-11-2018, 01:16 AM   #295
Gameguy326
Senior Member
 
Join Date: Aug 2015
Posts: 182
Re: MIT East Campus - Kendall Square Gateway | Cambridge

Quote:
Originally Posted by Jouhou View Post
I just dug through this whole thread, do we know what exactly is supposed to be replacing eastgate?
Something like this:

Gameguy326 is offline   Reply With Quote
Old 06-11-2018, 04:29 AM   #296
Jouhou
Senior Member
 
Jouhou's Avatar
 
Join Date: Nov 2015
Location: Portsmouth, NH
Posts: 551
Re: MIT East Campus - Kendall Square Gateway | Cambridge

Quote:
Originally Posted by Gameguy326 View Post
Something like this:


Oh. Gross. It'd be nice if they picked something that would fill in the skyline a bit better for that location. Eastgate is no architectural marvel but it's silhouette has definitely carved out a recognizable part of the skyline.
Jouhou is online now   Reply With Quote
Old 07-03-2018, 09:53 PM   #297
BeeLine
Senior Member
 
Join Date: Jan 2012
Posts: 7,759
Re: MIT East Campus - Kendall Square Gateway | Cambridge



Steel starting to push above ground level at the bldg 3 site in the foreground.


Bldg #3

Bldg #4

Bldg #4

Bldg #4



Bldg #5

Bldg #5


Last edited by BeeLine; 07-03-2018 at 10:06 PM.
BeeLine is offline   Reply With Quote
Old 07-04-2018, 01:01 AM   #298
Gameguy326
Senior Member
 
Join Date: Aug 2015
Posts: 182
Re: MIT East Campus - Kendall Square Gateway | Cambridge

Aw yeah, podium goin' up!
Gameguy326 is offline   Reply With Quote
Old 07-22-2018, 03:29 PM   #299
BeeLine
Senior Member
 
Join Date: Jan 2012
Posts: 7,759
Re: MIT East Campus - Kendall Square Gateway | Cambridge




Looks like foundation work has begun on bldg 1


BeeLine is offline   Reply With Quote
Old 07-22-2018, 03:38 PM   #300
BeeLine
Senior Member
 
Join Date: Jan 2012
Posts: 7,759
Re: MIT East Campus - Kendall Square Gateway | Cambridge

Steel breaking ground level at the bldg. 3 site.







Building #4 site.



Sorry for the fuzz, but it wss caused by another close encounter with a speeding cyclist,






Last edited by BeeLine; 07-23-2018 at 08:29 AM.
BeeLine is offline   Reply With Quote
Reply

Thread Tools Search this Thread
Search this Thread:

Advanced Search

Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

BB code is On
Smilies are On
[IMG] code is On
HTML code is Off
Forum Jump

Similar Threads
Thread Thread Starter Forum Replies Last Post
Novartis Campus | 181-211 Mass Ave, 22 Windsor Street | Cambridge - Kendall Sq stellarfun Development Projects 398 12-07-2016 07:17 AM
650 Eest Kendall | 650 East Kendall Street | Cambridge - Kendall Sq stellarfun Development Projects 75 03-17-2015 03:33 PM
Third Square | 303 Third Street | Cambridge - Kendall Sq Mike Development Projects 84 06-25-2011 11:39 PM
Cambridge's Kendall Square Seeks to Improve Its Brand kennedy General Architecture & Urban Planning 14 06-11-2010 03:38 PM
East Bayside gateway - Portland Patrick Greater New England 1 12-30-2009 12:09 PM


All times are GMT -5. The time now is 10:58 AM.


Powered by vBulletin® Version 3.7.3
Copyright ©2000 - 2018, Jelsoft Enterprises Ltd.